Dispute resolution | 27 October 2026
The evolution of construction dispute resolution: from litigation to adjudication
Construction disputes are nothing new. Complex contracts, tight programmes, multiple parties, payment pressures, design changes and site delays have caused disagreements across the construction industry for decades.
What has changed is how those disputes are resolved.
For much of the last century, parties were largely reliant on litigation and arbitration to resolve construction disputes. These processes remain important today, but the industry has gradually developed faster, more flexible ways of resolving disagreements.
The introduction of alternative dispute resolution and, in particular, statutory adjudication in the UK, represented a significant shift in the way construction disputes could be managed.
This first article in our three-part series looks at that evolution, from the traditional reliance on litigation and arbitration to the introduction of adjudication and the foundations of today's more flexible approach to dispute resolution.
The traditional approach: litigation and arbitration
For much of the 20th century, construction dispute resolution centred around two main options: litigation and arbitration.
Litigation
Litigation provided parties with a formal process for resolving disputes through the courts.
There were clear procedural rules, judicial oversight and an enforceable judgment at the end of the process. For complex disputes involving contractual interpretation, technical evidence or significant sums of money, the courts provided an established route to a final determination.
However, litigation could also be slow and expensive. Construction projects operate within tight financial and programme constraints. A dispute that remains unresolved for months or years can create additional pressure on cash flow, project delivery and commercial relationships.
There was also the question of publicity. Court proceedings are generally conducted in public, which could be unattractive where disputes involved commercially sensitive information.
For parties looking for a private alternative, arbitration offered another established route.
Arbitration
Arbitration allowed parties to resolve their dispute outside the court system.
The parties could appoint an independent arbitrator or tribunal, potentially with relevant legal or technical expertise, and proceedings could be conducted privately.
This made arbitration particularly attractive for complex construction and engineering disputes, including international projects where parties required a process capable of supporting cross-border enforcement.
However, arbitration was not necessarily quick or inexpensive.
As construction projects became larger, more technically complex and increasingly document-heavy, disputes could involve vast quantities of evidence and multiple technical and contractual issues. Arbitration could therefore become a lengthy process in its own right.
The construction industry needed alternatives that could resolve disputes more quickly and, where possible, without subjecting the parties to lengthy formal proceedings.
The emergence of alternative dispute resolution
Alternative dispute resolution, or ADR, developed as the construction industry looked for a broader range of ways to resolve disputes outside court proceedings.
ADR is an umbrella term that can include arbitration as well as negotiation, mediation, adjudication and dispute boards. These processes differ in formality and outcome, but they all offer alternatives to resolving disputes through litigation.
Over time, construction projects began to make greater use of quicker and more flexible mechanisms alongside arbitration. Negotiation and mediation allowed parties to seek a commercial settlement, while adjudication and dispute boards provided more structured routes for resolving issues during live projects.
The underlying principle was relatively straightforward: not every disagreement needed to end in court. Some disputes could be resolved through direct negotiation, while others benefited from a neutral third party helping the parties reach agreement or make a decision.
That keeps the distinction technically cleaner and avoids implying that arbitration sits outside ADR.
The growing role of mediation
Mediation became an increasingly valuable tool for construction disputes because it gave the parties greater control over the outcome.
Unlike litigation or arbitration, a mediator does not impose a decision. Instead, they help the parties understand the issues, explore potential solutions and negotiate a settlement.
This can be particularly useful where the parties need to maintain a commercial relationship.
Construction projects often involve employers, contractors, subcontractors, consultants and suppliers who may need to continue working together even after a disagreement has arisen.
A negotiated settlement can therefore sometimes achieve an outcome that a formal judgment or award cannot. However, mediation depends on the parties being willing to engage and compromise. Where an immediate decision is required, another process may be more appropriate.
This highlighted an important development in construction dispute resolution: different disputes could require different solutions.
Why construction needed a different approach
The causes of construction disputes have remained relatively consistent.
Disagreements can arise from:
- Ambiguous or poorly drafted contract terms
- Delayed or incomplete design information
- Variations and changes in scope
- Payment disputes
- Extension of time claims
- Loss and expense claims
- Defective work
- Poor communication
- Incorrectly issued notices
- Disagreements over responsibility for delay.
These issues can arise while a project is still being built – which creates a particular challenge.
A traditional process that takes years to reach a final determination may not address the immediate commercial problem facing the parties.
For example, a contractor experiencing a payment dispute may need a decision quickly because the consequences of delayed payment can extend far beyond the original disagreement.
The industry therefore needed a mechanism that could provide a rapid decision while allowing the parties to continue with the project. In the UK, one of the biggest changes came in the 1990s.
The introduction of statutory adjudication
The Housing Grants, Construction and Regeneration Act 1996 introduced a statutory right to adjudicate certain construction disputes. This was a major turning point for the UK construction industry.
Adjudication gave parties to qualifying construction contracts the ability to refer disputes to an adjudicator and obtain a rapid decision.
The process was designed to operate within a much shorter timeframe than traditional litigation or arbitration. In many cases, the adjudicator is required to reach a decision within 28 days of the referral, subject to the statutory and contractual provisions that apply.
This fundamentally changed the options available to construction professionals. Instead of waiting months or years for a dispute to reach a final determination, a party could obtain an interim binding decision within weeks.
The process became particularly significant for payment disputes, where the consequences of unresolved disagreements could have an immediate impact on contractors and subcontractors.
Adjudication is often described as a "pay now, argue later" process because an adjudicator's decision is generally binding unless and until the dispute is finally determined through litigation, arbitration or settlement.
This approach recognised an important reality of construction: projects need to keep moving, even when the parties disagree.
For many domestic construction disputes, adjudication became a practical formal route rather than something reserved for the end of a long-running dispute.
A new direction for construction disputes
The introduction of statutory adjudication did more than create another dispute resolution mechanism. It changed expectations about how quickly construction disputes could be resolved.
The industry was no longer limited to choosing between traditional court proceedings and arbitration. Parties increasingly had access to processes that could be more proportionate to the nature and urgency of a dispute.
But it did not make litigation or arbitration obsolete. Both remain important when a final determination is required, when disputes are particularly complex, or when the circumstances make a formal process appropriate.
Instead, the landscape became more varied. Construction dispute resolution began to move away from the idea that every disagreement should follow the same route.
From formal disputes to flexible resolution
The historical development of construction dispute resolution shows a clear pattern.
Traditional litigation and arbitration provided established and important mechanisms for resolving disputes, but their limitations encouraged the development of alternatives.
Negotiation and mediation created opportunities to resolve disagreements without a formal determination. Statutory adjudication then introduced a faster route to an interim binding decision for qualifying construction disputes in the UK.
Together, these developments laid the foundations for the modern construction dispute resolution landscape. Today, project teams have a much wider range of options available to them, and the question is no longer simply whether a dispute should go to court.
Instead, parties can consider the nature of the disagreement, its urgency, the commercial relationship and the outcome they need before deciding how to proceed.
And that brings us to the present.
In the second article in this series, we look at how construction disputes are dealt with today, why modern dispute resolution has become more multi-layered, and how the industry has moved towards choosing the right process for the circumstances.
